ggshankar
One of my user has updated the actuals of a task which has not started yet
and we have updated the project plan also by mistake without noticing it. Is
there a way to revert back these changes in the project plan so that it shows
the exact start date and not the erroneous one?
Please advise.
Thanks in advance.
Thanks & Regards,
Shankar