keysdoctor said:
I have 10 physicians covering one call schedule. I defined the task as a
shift from 5pm to 8am daily, 24 hour schedule. How do I assign the 10
physicians (work resources) to the task and have one physician do each of the
calls?
keysdoctor,
Maybe I'm missing something but it seems to me that the 10 physicians
are actually "on-call", that is, there is not a defined set of calls, it
will vary from shift to shift.
Project is structured to schedule and track a defined set of tasks. If
the tasks change, the plan must be changed, manually. In your scenario,
it certainly is easy enough to define a shift as a task and assign 10
physicians to that task but the only way to have a specific physician
handle a specific call is to create a separate task for that call and
assign that physician to it - kind of defeating the idea of setting up
the single shift task in the first place.
John
Project MVP