C
Cynthis PMP
I have created a couple of formulas/functions that use the start and end date
of the project , along with the current date and the percent complete. Based
on the calulation I show a 'stoplight' for each task. Currently the problem
is unless you modify something in your plan the formulas and fuctions don't
update. Is there a way to get the formulas and fuctions to systematically
update?
Thanks
of the project , along with the current date and the percent complete. Based
on the calulation I show a 'stoplight' for each task. Currently the problem
is unless you modify something in your plan the formulas and fuctions don't
update. Is there a way to get the formulas and fuctions to systematically
update?
Thanks