How to get rid of superfluous "Change Working Time" calendars

P

Peter Rooney

Good afternoon, all!

I have recently removed all references to resources who are no longer
working on tasks in my plan from the resources column.

However, when I go into "Change Working Time", I can still see references to
all of the deleted resources.

Ideally, I would only like to see "active" resources in this list - how can
i get rid of the rest?

Thanks in advance

Pete
 
J

Jan De Messemaeker

Hi Peter,

Aren't the calendars you see base calendars rather than resource calendars?
Those are deleted through Organizer, Calendars

An when you say you deleted "all references" to the resource, that worries
me a bit. In fact, deleing it from the resource sheet deletes all other
"references". Did you delete them from the resoruce sheet as well?

And of course... the file isn't connected to an open resource pool is it?
 
P

Peter Rooney

Good morning, Jan,

Sorry for not replying to you until this morning - some server problem or
other meant that I could read the boards, but not reply or post.
Just so you can sleep tonight (!), The Gantt view of my plan now only
contains internal resources. I removed the external resources in resource
view, and the calendars for them that had previously appeared in "Change
Working Time" have now gone, too. And no, the file wasn't connected to an
open resource pool.

Thanks for your advice and for replying to my question

Regards

Pete
 