S
Steve
I'm constructing and statusing a simple overview plan, so using simple FS
fixed duration tasks with settings for days (not hours). All the tasks are
start at the beginning of the day and finish at the end.
When for example I update a 5 day task at 50% (a simple way to say it's
started and not finished) and owing to slip the remainder is scheduled to the
status line then I get a split 12.5 day task which is 20% complete. (? Not
so good.) But the task is scheduled to finish at midday and the successor to
start at midday on the same day where my client would prefer to see separate
days for finish and start. Any suggestions about set up to give beginning of
the day only starts, or using a different approach please?
fixed duration tasks with settings for days (not hours). All the tasks are
start at the beginning of the day and finish at the end.
When for example I update a 5 day task at 50% (a simple way to say it's
started and not finished) and owing to slip the remainder is scheduled to the
status line then I get a split 12.5 day task which is 20% complete. (? Not
so good.) But the task is scheduled to finish at midday and the successor to
start at midday on the same day where my client would prefer to see separate
days for finish and start. Any suggestions about set up to give beginning of
the day only starts, or using a different approach please?