I have a project with 1200 lines with diferents task and specific duration,
my problem is that I don't have the start date y only have the final date
(deadline).
I made a test working with predecessors task and "Start to Finish" this
working fine, but I need to change 1,200 lines, exist something more
automatic to recalculate the all project task from the end date ??
my problem is that I don't have the start date y only have the final date
(deadline).
I made a test working with predecessors task and "Start to Finish" this
working fine, but I need to change 1,200 lines, exist something more
automatic to recalculate the all project task from the end date ??