A
ant1983
Hi...
I have a task called 'Design Document & Sign Off' with subtasks as follows:
Define the HP SA architecture (2 days)
Develop HP Architecture and design document (2 days)
Review and provide feedback on the System Architecture (1 day)
Deliver completed System Architecture (0 days - milestone)
The problem is that the main task; 'Design Document & Sign Off' calculates a
total of 4.4 days and not 5 days as it clearly is suppose to...
This happens throughout my plan...
How come?
Thanks!!
I have a task called 'Design Document & Sign Off' with subtasks as follows:
Define the HP SA architecture (2 days)
Develop HP Architecture and design document (2 days)
Review and provide feedback on the System Architecture (1 day)
Deliver completed System Architecture (0 days - milestone)
The problem is that the main task; 'Design Document & Sign Off' calculates a
total of 4.4 days and not 5 days as it clearly is suppose to...
This happens throughout my plan...
How come?
Thanks!!