Is it possible to set new tasks to a specific date

L

la0d0g

Is there a way to have each new task added to a project start/end on a
specific date (NOT the project start date or current date)? Thanks in
advance!
 
R

Rod Gill

Yes,

Enter a Start or Finish date. Note however you now have to manually maintain
these dates until the task finishes. You get much better schedules if you
only ever link tasks together.
 
C

Catfish Hunter

Go to Tools>Options>Schedule. Here you have 2 options to have new task start
on. Good Luck!
 