R
Rebel.Ranter
Is a lead time mandatory or optional?
I have two tasks that have a *finish to finish* dependency with a lead
time of 2 days
Task A duration 8 days
Task B duration 10 days
The lead time is 2 days between A & B
My question is this, when I specify the lead time am I saying?:
(a) B *must* finish 2 days before A at all times, i.e. a mandatory gap
of 2 days is required.
or
(b) B can finish 0-2 days before A, i.e. 2 days, 1 days, or same day
Thanks in advance for your help on this, putting it into MS Project
doesn't make it clear to me, maybe it's just the way I am entering it.
I have two tasks that have a *finish to finish* dependency with a lead
time of 2 days
Task A duration 8 days
Task B duration 10 days
The lead time is 2 days between A & B
My question is this, when I specify the lead time am I saying?:
(a) B *must* finish 2 days before A at all times, i.e. a mandatory gap
of 2 days is required.
or
(b) B can finish 0-2 days before A, i.e. 2 days, 1 days, or same day
Thanks in advance for your help on this, putting it into MS Project
doesn't make it clear to me, maybe it's just the way I am entering it.