Hi
I have a project schedule that I have used to plan tasks for a 6 person
team.
I am starting to track progress now and am filling in % complete for
some of the tasks.
I am wanting to level the project - so that based on todays remaining
amount of work - i can see the predicted project end date - but it
doesnt seem to allow me to do this.
I have some tasks that are completed - that are still showing on the
schedule to start in a weeks time. Is project clever enough to free up
that resource for that task - or will i need to manually remove the
resource for any tasks that is 100% complete?
I have a project schedule that I have used to plan tasks for a 6 person
team.
I am starting to track progress now and am filling in % complete for
some of the tasks.
I am wanting to level the project - so that based on todays remaining
amount of work - i can see the predicted project end date - but it
doesnt seem to allow me to do this.
I have some tasks that are completed - that are still showing on the
schedule to start in a weeks time. Is project clever enough to free up
that resource for that task - or will i need to manually remove the
resource for any tasks that is 100% complete?