I have two partially overlapping activities with the same resources assigned.
What I'd like to do is to make activity start date have priority over
resource allocation so that when I level resources the activities still start
on the same date, but a resource's time is divided by the two activities.
I.e. Act. 1 sept. 1. - oct. 1. and act. 2 sept. 15 - oct. 15., resource X
assigned to both. The result I want is that X is assigned 100% to act. 1 from
sept. 1. to sept 14., then 50% on each activity from sept. 15. to oct. 1.,
and then 100% to act. 2 from oct. 2. to oct. 15.
Is this possible to achieve?
What I'd like to do is to make activity start date have priority over
resource allocation so that when I level resources the activities still start
on the same date, but a resource's time is divided by the two activities.
I.e. Act. 1 sept. 1. - oct. 1. and act. 2 sept. 15 - oct. 15., resource X
assigned to both. The result I want is that X is assigned 100% to act. 1 from
sept. 1. to sept 14., then 50% on each activity from sept. 15. to oct. 1.,
and then 100% to act. 2 from oct. 2. to oct. 15.
Is this possible to achieve?