Linking from end date of summary task.

R

RWR

Is it possible to link to a sub task (completion of the task) and link
backwards within this task to arrive at a start date for the task? I am
linking to an external project and want the external milestone date to be the
completion date of the task in my project. I then want to schedule backwards
in my project to the start date of the task.

thanks,


RWR
 
J

Jan De Messemaeker

Hi,

If I understand you well, you are describing a perfect circular relationship
B waits for A to finish, then A waits for B to start.
Impossible, by all means: there is no solution to that.
Should you atrrive to make that construction in Poject, there will be no
more calculations within those files untiil you undo the impossibility.
Hope this helps,
 