Linking Tasks

  • Thread starter Michael Longdin
  • Start date
M

Michael Longdin

My task linking appears to have stopped working how I would expect it to (and
how it used to).

To create a basic finish-start dependency between two tasks, let's say of 5
days effort and duration each, I highlight them and then click 'link tasks'.
I would expect this to show the first task starting today and then the second
task to start 5 days later - however, whilst the link has been created, both
tasks show as starting today.

I have checked that it has been set up as a finish-start date and the only
constraint is 'start asap'

Is there some other setting that I am missing that will prevent the
dependency from being created properly?
 
M

Michael Longdin

Great. Thank you very much (not sure how/when that option got altered but it
has resolved my problem)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top