S
Sandy
I have created a fixed work task of 8 hours and assigned a
100% dedicated resource to that task. This resource is
associated with the Standard Calendar which indicates that
each workday is 8 hours, plus there are no holidays or
other outages associated with this resource on this date.
MS Project is calculating that it will take 1.33 days
duration to complete this task. If I force the duration
to 1 day, Project calculates that the resource is now 133%
allocated. I don't understand why the 100% allocated
resource cannot complete this task in one day without
being overallocated - can anyone help me? Thanks!
100% dedicated resource to that task. This resource is
associated with the Standard Calendar which indicates that
each workday is 8 hours, plus there are no holidays or
other outages associated with this resource on this date.
MS Project is calculating that it will take 1.33 days
duration to complete this task. If I force the duration
to 1 day, Project calculates that the resource is now 133%
allocated. I don't understand why the 100% allocated
resource cannot complete this task in one day without
being overallocated - can anyone help me? Thanks!