Hi hammering4u,
I'm not sure I follow your scenario exactly. What I assume you are looking
for is to show how many calendar days (including non-working time during the
weekend) have passed from the start of the task to the finish of the task.
You can use a custom duration (Duration1, Duration2, etc.) to calculate the
number of calendar days. If I am incorrect, please let us know and we'll
try again. Based on the above assumption:
Create a new calendar (Tools>Change Working Time). Copy the Standard
calendar, name it (I used 7Day) and make Saturdays & Sundays working days.
Then insert a custom duration field ([Duration1] for example) in the task
table. Choose Tools>Customize Fields and select the [Duration1] field.
Click the Formula... button and use the following formula:
ProjDateDiff([Start],[Finish],"7Day")
In the Customize fields dialog box, click the Use Formula option for the
task and group summary rows.
This will calculate the number of calendar days between the start of the
task and the finish of the task using the 7Day calendar.
I hope this helps. Let us know how you get along.
Julie
hammering4u said:
Working in construction, we need to track overall calendar days for the
client, 7 days a week. We need to enter working days in a regular 5-day
work
week. I can't find a way to adjust the calendar to allow this. We are
now
entering 9 days of time for a task that takes 7 in order to allow for
non-working weekends. We would like Project to do this adjustment
automatically