M
Mr Mike
Regarding MS - Project 2003 SP2. When I open a project file the Gantt
display defaults to a date over two years ago.
All tasks start after 5/10/07.
The project information has a start date of 5/10/07.
File properties all are as expected.
But the Gantt starts up from 11/28/2004.
Is there somewhere else that could be responsible. I've checked all
the options and can't see anything.
Thanks to all who try to answer this one!
display defaults to a date over two years ago.
All tasks start after 5/10/07.
The project information has a start date of 5/10/07.
File properties all are as expected.
But the Gantt starts up from 11/28/2004.
Is there somewhere else that could be responsible. I've checked all
the options and can't see anything.
Thanks to all who try to answer this one!