K
King Kong
Environment:
MS Project Professional 2003
Hi
now I have another issue.
I have several external suppliers delivering project plans.
Not all the time I need all details to compile my own plan.
I know I can import plans into my own one.
Can I also import only a subset, certains tasks, or certain group of
tasks?
Sometimes it would also be helpful to be able to add my tasks between
their tasks. Are those things possible?
Kay
MS Project Professional 2003
Hi
now I have another issue.
I have several external suppliers delivering project plans.
Not all the time I need all details to compile my own plan.
I know I can import plans into my own one.
Can I also import only a subset, certains tasks, or certain group of
tasks?
Sometimes it would also be helpful to be able to add my tasks between
their tasks. Are those things possible?
Kay