My Tasks /Time Sheets in MPP 2007

M

Muthukkumaran

Hi,

I am configuring MPP 2007. I have some issues in accessing My tasks/ Time
sheets. I did not found this issues in my test server. We have installed
Windows Updates two days back (configured to update every Tuesdays).

1. Today, I'm trying to assign some tasks to myself. I have created project
and created tasks and assign all tasks to myself. The 'My Tasks' view shows
No tasks assigned. I have also unchecked 'Show Only Current Tasks' option.
But still not showing any task. My Time sheet showing the tasks assigned to
me. I also tried to import my tasks to Outlook. No tasks updated.

2. I have created some other new tasks and assign to another resource. Now
My Tasks showing the tasks assigned to him. But he said no tasks listed to
his My Tasks view.

3. I am trying to update MyTime sheet for a period (Weekly) and submitted
Successfully with 'System generated automatic approval' Message. But the
Project Center shows 0% complete in all my tasks even after publishing the
project.

Any help would be sincerely appricaited.
Thanks in Advance.

Regards
Muthukkumaran
 