S
Steve House
This is not an exception - W=D*E still holds true. First remember that
duration from when work begins until it is done. Also remember that Project
does each resource's work calculations independently of any other resources.
If two resources are on a task and one starts later than the other or
finishes his part of the task before the other, the TASK duration is the
time between when the FIRST starting resource and the LAST finishing
resource. But when you view each resource separately, W=D*E always holds
true.
In your example, resource A is initially assigned, duration = 10 days and
work = 80 hours. Now B is added. The work is split and each resource does
40 hours of work, running in parallel. Each one works five days, the same
five days, so the task duration is also 5 days. But now you increase A to
200%. He still does 40 hours of work, but he does it twice as fast. He
finishes his share in 2.5 days and goes away. But B is still plugging away
at 100% with 2.5 days of work still to do. Total task duration remains at 5
days and the fact that A left after 2.5 days doesn't change it.
FYI - it's actually impossible for A to work at 200% unless he has two
heads. 100% means that in 8 hours of working time you get 8 hours worth of
full-time productivity output. 200% means that in 8 hours of working time
you'll get what takes a normal person 16 hours to accomplish. Unless A is
an aggregate resource consisting of more than one individual - 5 carpenters
represented in the resource list as a single entry "carpenters" with a max
avail of 500% - that's simply going to be physically impossible to achieve.
For a single worker, 100% is the maximum you can ever reasonably expect them
to do.
HTH
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
duration from when work begins until it is done. Also remember that Project
does each resource's work calculations independently of any other resources.
If two resources are on a task and one starts later than the other or
finishes his part of the task before the other, the TASK duration is the
time between when the FIRST starting resource and the LAST finishing
resource. But when you view each resource separately, W=D*E always holds
true.
In your example, resource A is initially assigned, duration = 10 days and
work = 80 hours. Now B is added. The work is split and each resource does
40 hours of work, running in parallel. Each one works five days, the same
five days, so the task duration is also 5 days. But now you increase A to
200%. He still does 40 hours of work, but he does it twice as fast. He
finishes his share in 2.5 days and goes away. But B is still plugging away
at 100% with 2.5 days of work still to do. Total task duration remains at 5
days and the fact that A left after 2.5 days doesn't change it.
FYI - it's actually impossible for A to work at 200% unless he has two
heads. 100% means that in 8 hours of working time you get 8 hours worth of
full-time productivity output. 200% means that in 8 hours of working time
you'll get what takes a normal person 16 hours to accomplish. Unless A is
an aggregate resource consisting of more than one individual - 5 carpenters
represented in the resource list as a single entry "carpenters" with a max
avail of 500% - that's simply going to be physically impossible to achieve.
For a single worker, 100% is the maximum you can ever reasonably expect them
to do.
HTH
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
vikas said:W=DxE has exceptions.
take a task. say duration = 10 days
assign resource A (100%), so work = 10 days
so far so good.
ensure task type is FIXED UNITS
ensure task is effort driven.
assign another resource B (100%)
work remains at 10days - good
duration reduces to 5 days - good
resource units = 200% (A and B)
so far so good..
NOW increase assigned units for A to 200%
total units 300% (A @ 200% and B @ 100%)
duration remains at 5 days, work remains at 10 days. WHY WHY WHY?
below is a cut and paste of from MS Project.
task name/dur/type/effort driven/work/resource names
task 5 days Fixed Units Yes 10 days "A[200%],B"
For Lamby, I would suggest, as the PM, you drive MSP, dont let MSP drive
you
(crazy). use KISS.
Regards,
Vikas
(e-mail address removed)
lamby74 said:Thanks Steve. You and Dale both gave really thoughtful (and
time-consuming,
I am sure, ) answers. I am carefully studying both of your responses and
will be showing them to my boss shortly. I'll let you know how it all
turns
out.
In the meantime, I welcome more opinions. The more upfront and honest
(even
if hard-edged) the better.
Thanks all.