Not changing end date of task

J

Jeroen

Hello

Is it possible to keep the end date of the task like i planned instead
of changing it after filling it the real end date of the task? I wat to
seen afterworts what i have planned and what be at the end.
 
R

Rod Gill

Hi,

When a Task is complete, finish always equals actual finish. What you need
to do is save a baseline (Tools, Tracking, Set Baseline) then view the
Tracking Gantt chart to see the before and after.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com