Winston Smith 6076
I have a small software project where I have a project manager working 3
hrs/week on the six week project. I have not been able to properly document
this task and resource in Project and am looking for advice. I attempted to
indicate the resource at 15%, approximately 3 hours/week, but that was not
successful, as Project recalculated the time as 2 weeks duration.
I am looking to schedule the resource for the full 6-weeks, but at 15%. How
would I do this?