I;m going crazy..
I paste a group of task name and start and finish dates from Excel into
Project but the resulting dates in Project are shifted back by 4 years. Ie:
3/5/2005 becomes 3/5/01. But if I select the dates in Project and paste
them back into Excel they are correct again. If I paste manually entered
dates in Project to Excel the are also offset.
What is going on?
Thanks