D
DanG
I asked a similar question about 18 months ago, but found no solution, so I'm
trying again... The project has:
- one machine that operates 24 hours/day
- two people, each working 8 hours/day
- two tasks, each of which is 48 hours long, with a Start-Start relationship
- each task can only have use the machine for 6 hours each day
- each task requires BOTH one person and the machine or no work can be done
How can I set this up to accurately plan the tasks with the correct amount
work for all resources and correct durations for both tasks?
It seems as though some kind of logical AND is needed for the resources, but
I don't know how to achieve that.
Thanks,
DanG
trying again... The project has:
- one machine that operates 24 hours/day
- two people, each working 8 hours/day
- two tasks, each of which is 48 hours long, with a Start-Start relationship
- each task can only have use the machine for 6 hours each day
- each task requires BOTH one person and the machine or no work can be done
How can I set this up to accurately plan the tasks with the correct amount
work for all resources and correct durations for both tasks?
It seems as though some kind of logical AND is needed for the resources, but
I don't know how to achieve that.
Thanks,
DanG