T
Tim_Ver
I have a project I am doing now with dates that will change alot. I want to
use predecessors, but never have before so not sure how to set them up. I
have one main task and under it are about 100 subtask and each of those
subtask have three subtasks of their own. The reason I want to use
predecessors is this depends on when hardware comes in so as it does I need
to change dates which will then change the overall dates for the main task.
If anyone has a project plan where they have done this or an example they can
email me please feel free at (e-mail address removed) also explain here how to do
this. I have tried and get the explanation in MS project 2003 that I can not
link a sumary task to on of it's subtasks.
Thanks Much.
use predecessors, but never have before so not sure how to set them up. I
have one main task and under it are about 100 subtask and each of those
subtask have three subtasks of their own. The reason I want to use
predecessors is this depends on when hardware comes in so as it does I need
to change dates which will then change the overall dates for the main task.
If anyone has a project plan where they have done this or an example they can
email me please feel free at (e-mail address removed) also explain here how to do
this. I have tried and get the explanation in MS project 2003 that I can not
link a sumary task to on of it's subtasks.
Thanks Much.