G
Glen
I found a problem in MS Project 2000 and would like to know if anyone can
help please.
In one of my project files, if I choose the menu option Tools, Tracking,
Save Baseline, then click OK, I should see the entries in columns "Start" and
"Finish" copied to columns "Baseline Start" and "Baseline Finish". But this
doesn't happen - the baseline fields still show NA. It works OK if I try
this on the same file in Project 2007, and also in Project 2000 for some
other files. Is there a known bug? If so is it fixed in a service pack (I'd
like to keep Project 2000 for now if possible).
help please.
In one of my project files, if I choose the menu option Tools, Tracking,
Save Baseline, then click OK, I should see the entries in columns "Start" and
"Finish" copied to columns "Baseline Start" and "Baseline Finish". But this
doesn't happen - the baseline fields still show NA. It works OK if I try
this on the same file in Project 2007, and also in Project 2000 for some
other files. Is there a known bug? If so is it fixed in a service pack (I'd
like to keep Project 2000 for now if possible).