J
Jaya
Hey all,
I have a problem comprehending with what is baseline start/finish, actual
start/finish, start/finish columns.
- I generally use start/finish, and I save baseline.
For e.g. I assign a resource for 3 days but he finishes his work in one day
and he updates in his calender(in Microsoft Outlook through web access) that
his work is 100% in the same day. When I check in Microsoft Project, his work
is complete but the Finish date and actual finish date is still in 3 days,
but the person has finishd the work in one day. Why is that so ?
- All the reports is based on each project! Is there any way of customizing
a report based on all the projects in the project server because that
involves all resources and we could know how many resources are allocated to
ho many projects ?
Somebody helpp....I am feeling so stuck .
Thanks,
Jaya
I have a problem comprehending with what is baseline start/finish, actual
start/finish, start/finish columns.
- I generally use start/finish, and I save baseline.
For e.g. I assign a resource for 3 days but he finishes his work in one day
and he updates in his calender(in Microsoft Outlook through web access) that
his work is 100% in the same day. When I check in Microsoft Project, his work
is complete but the Finish date and actual finish date is still in 3 days,
but the person has finishd the work in one day. Why is that so ?
- All the reports is based on each project! Is there any way of customizing
a report based on all the projects in the project server because that
involves all resources and we could know how many resources are allocated to
ho many projects ?
Somebody helpp....I am feeling so stuck .
Thanks,
Jaya