Project 2000 Task Question

M

Marilyn

I have a project with several Task and the Work on one Task has completely
come to a halt and I'm not sure if it will begin again. Is there a way I can
specify that Work has stopped on the task without affecting the End Date of
my Project?

Please Help!!

Thanks,
 
J

Jan De Messemaeker

Hi,

Yes
Insert the column "Remaining Work" and put it to 0
Or simply put the tak to 100% done.
HTH
 