Project 2003 Resource Usage View

B

Ben

Hi,

With Project 2003 and Project Server 2003, the Resource Usage View presents
the tasks assigned to each resource in the project. But it also presents the
other projects where each of these resources are also assigned.
Example:
Ordering equipment. <------ Current project task
Release Post-Mortem <------ Current project task
CTS 2006 Planification.Published <------- Other project tasks summary

Is there a way to disable the view of other projects that uses the same
resources?


Thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top