Project 2007 Question on use of the Calendar

P

prsiv

Hello,

I have entered about 400 tasks in Project 2007. I now need to modify the
calendar to reflect the Thanksgiving and Christmas holidays. I added both of
these holidays to the standard calendar but my tasks did not update to use
the information. I added a new calendar with these holidays and changed all
tasks to use the new calendar without any luck. My last attempt, I changed
each resource to use the newly defined calendar. No joy....

If you could give me any suggestions I would appreciate it. Is there a
'recalculate' project?
 
M

Mike Glen

Hi prsiv ,

Welcome to this Microsoft Project newsgroup :)

Yes - F9. Set it in Tools/Options/Calculation tab - to Automatic.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 