Hello,
I have entered about 400 tasks in Project 2007. I now need to modify the
calendar to reflect the Thanksgiving and Christmas holidays. I added both of
these holidays to the standard calendar but my tasks did not update to use
the information. I added a new calendar with these holidays and changed all
tasks to use the new calendar without any luck. My last attempt, I changed
each resource to use the newly defined calendar. No joy....
If you could give me any suggestions I would appreciate it. Is there a
'recalculate' project?
I have entered about 400 tasks in Project 2007. I now need to modify the
calendar to reflect the Thanksgiving and Christmas holidays. I added both of
these holidays to the standard calendar but my tasks did not update to use
the information. I added a new calendar with these holidays and changed all
tasks to use the new calendar without any luck. My last attempt, I changed
each resource to use the newly defined calendar. No joy....
If you could give me any suggestions I would appreciate it. Is there a
'recalculate' project?