Hello gvs,
The Project 2007 method of changing working time is a bit different, as
you have discovered. To make a selected day nonworking:
Tools > Change Working Time and scroll the calendar to the month you
need.
Select the day or days you wish to make non-working.
Click the Exception tab towards the bottom of the dialog box, if
necessary.
Enter in a name for the exception -- for example, the name of the
holiday. The start and Finish area should fill in if you press ENTER or
TAB.
The day or days should now be nonworking time.
If 8:00 - 5:00 pm does not accurately express the working time, you will
need to change the working hours for all working days.
Click the Work Weeks tab and then click the Details... button.
Select the working days (you can click and drag to select Monday through
Friday if needed) and use the options to the right of the dialog box to
either set the days as nonworking, working, or specific working times.
The Help button in the Change Working Time dialog box and the Help
button in the Details dialog box will give additional information that
you will find helpful as well.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project