Project: How do I get a fixed date off a task?

M

Michelle S.

My tasks have start "as soon as possible" as their constraint types. Each
time I try to set a predecessor on them, I get an error message warning me of
a scheduling constrint, and saying that it's link to a task that cannot move.
I did not set any tasks that couldn't move, and didn't set the date on any
of the tasks -- I just want to use normal dependencies to automatically set
the start dates. How do I fix this?
 
T

Trevor Rabey

Perhaps you have accidentally set a Date Constraint (other than ASAP which
isn't really a constraint).
I find that it is always useful to show the Indicators column so that you
can see if this has happened.
--
Trevor Rabey
0407213955
61 8 92729485
Perfect Project Planning
www.perfectproject.com.au
 
J

Jan De Messemaeker

Michelle,

Maybe one or more of the successor tasks have an actual start date and/or
actual work?
HTH
 