Project Server 2003 to-do list start and finish dates

S

Sandy

We are using Project Server 2003. In the to-do list functionality, the start
and finish dates default to the current date, and cannot be changed. Is this
a functionality probelm or a configuration problem. If it is the latter,
where is this setting located?
 
M

Mike Glen

Hi Sandy,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top