Project start date

G

Glyn Curtis

I have a programme that works well time wise but need to change the start
date but keeping all the following tasks to follow suit....how do I do that
please?

Glyn Curtis
 
M

Mike Glen

Hi Glyn,

Welcome to this Microsoft Project newsgroup :)

Look for the Adjust_Dates macro in the Analysis toolbar or
Tools/Macro/Macros...

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 