M
M. Schmidt
I work on a rather disorganized team. They want me to track all projects and
incoming task requests in Project 2003. This is fine, except that Project
wants dates, and scheduling anything around here is a nightmare. Priority is
given to the most politically influenced projects/tasks and/or the "squeeky
wheel". It is not uncommon at all for projects/tasks to begin, only to be put
on hold when something "hotter" comes along. With that in mind, I have
several project tasks that have been put on hold indefinitely. I don't want
to delete the project/task altogether because if I do it will likely be
forgotten about completely. (We have a formal change request process that
SHOULD track these things outside of Project, but Management doesn't enforce
it, so no one uses it.)
How can I indicate that someting has been put on hold indefinitely in
Project 2003 such that: a) the task isn't flagged as "behind schedule" and b)
doesn't send reminders out to the resource reminding them that the task is
behind schedule when it really isn't - it's on hold? I tried simply deleting
the dates, but Project just inserts today's date and entering a duration of 1
day on it's own.
Any suggestions? Should I just remove them from Project altogether and paste
them into a spreadsheet or something?
incoming task requests in Project 2003. This is fine, except that Project
wants dates, and scheduling anything around here is a nightmare. Priority is
given to the most politically influenced projects/tasks and/or the "squeeky
wheel". It is not uncommon at all for projects/tasks to begin, only to be put
on hold when something "hotter" comes along. With that in mind, I have
several project tasks that have been put on hold indefinitely. I don't want
to delete the project/task altogether because if I do it will likely be
forgotten about completely. (We have a formal change request process that
SHOULD track these things outside of Project, but Management doesn't enforce
it, so no one uses it.)
How can I indicate that someting has been put on hold indefinitely in
Project 2003 such that: a) the task isn't flagged as "behind schedule" and b)
doesn't send reminders out to the resource reminding them that the task is
behind schedule when it really isn't - it's on hold? I tried simply deleting
the dates, but Project just inserts today's date and entering a duration of 1
day on it's own.
Any suggestions? Should I just remove them from Project altogether and paste
them into a spreadsheet or something?