re-do a task

S

Spencer Hutton

i have a task, "Run Comparison Report" with a few other tasks dependant on
it. also this task has 2 predecessors when i check the report and there are
errors that need to be fixed, i need to tell the project to go back and
repeat the predecessors, and re adjust the schedule. i hope this makes
sense, i am a project newbie. TIA
 
J

Jan De Messemaeker

Hi Spencer,

You have the following options:
- Copy/Paste the tasks to be redone and reschedule them.
-Or, Put these tasks to 0%complete, select them, and through tools,
tracking, Update Project, Reschedule work to... for selected tasks.

The first option will preserve the work done the first time and seems
preferrable as it better reflects reality.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top