Removing a resource from a task?

S

shortnsweet1970

Hi, I'm fairly (really) new to MS Project, and am using the "by guess and by
gosh" method of figuring things out when colleagues can't seem to help. I've
run into a problem/question that my colleagues don't seem to think is
fixable, so I wanted to post it here.

First a short overview of what I do with MS Project - I use MS Project as a
glorified time sheet at the moment. We have line projects with tasks that
last all year, have no time limit, etc. Everyone is just thrown under all the
tasks they do, so they can fill in how much time they spend on each task.

My problem is, some colleagues are complaining that their task sheet (in EPM
for a web environment) is too full, with old or incorrect projects and tasks
still visible. These are often old projects that can be closed, but
occasionally there are tasks from current projects that the project manager
thought these colleagues might do. It turns out that they don't, so they
don't want to see them anymore.

I know they can do "hide", but I was trying to come up with a way to clean
it up and have them removed from the task altogether. It doesn't seem
possible. Everywhere I look, I see ways to add people, but no way to say,
"oops, that was a mistake, I need to remove them". Does anyone have a
suggestion?

Thank you in advance.
 
M

Mike Glen

Hi ,

If you're using a server, please try posting on the server newsgroup.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
S

shortnsweet1970

I'm sorry. I don't really understand FAQ item 24. My company uses a server,
but I considered this a "general question". I didn't think it had anything in
particular to do with a server, but I guess I'll copy my post and put it
there. Like I said, I'm really a beginner with MS Project and basically only
know how to turn it on and do what I've been taught to do (which is making a
project from a company template, adding tasks and resources, and that's about
it).

Anyway, sorry for the inconvenience.
 
J

JulieS

Hello shortnsweet1970,

I believe the reason why Mike directed you to the Project Server
newsgroup is because, as I understand your question, you want to remove
tasks from user's timesheets. The timesheet is part of Project Web
Access which is the web component working with Project Server.

If you wish to remove a resource from a task in Project Professional,
you certainly can. Open the project file in Project Professional, click
on the task and the Gantt chart view, click the Assign resources button
on the Standard toolbar, select the name of the resource you wish to
remove, and click the "remove" button.

However, to get that assignment removed from the timesheet you need to
make changes to the information stored in Project Server and visible to
your users in Project Web Access. Sorry, that detail I don't know and I
would suggest posting to the server newsgroup as well.

While many of the responders who work with server also read and respond
in this newsgroup, their "first stop" is usually the server newsgroup.
The separation (what is the desktop Project process, what is a server
process, and what is a PWA process) is fuzzy at times -- even to us.

No inconvenience on our part -- Mike was just trying to find you a
quicker answer by directing you to a newsgroup where the "server gurus"
are focused.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top