Report for Task not completed

S

Scott

I'm going to assume that you have the original completion
date baselined. If not, then set the baseline finish date
as the original finish date.

After that, create a filter for those tasks where the
finish date is greater than the baseline finish date. You
can use this filter to create printable reports.

Scott
 
B

Brad

Great Thanks!
Brad
-----Original Message-----
I'm going to assume that you have the original completion
date baselined. If not, then set the baseline finish date
as the original finish date.

After that, create a filter for those tasks where the
finish date is greater than the baseline finish date. You
can use this filter to create printable reports.

Scott


.
 