reports

R

Rach

I have a consolidated project and Im trying to print a To-Do-List of a single
resource across the insert( subproject) project. However the To-Do-List is
generated without indicating which task belongs to which inserted project.

Is there a way to edit this report to show this? Task ID doesn't help either.

Thanks
 
J

John

Rach said:
I have a consolidated project and Im trying to print a To-Do-List of a single
resource across the insert( subproject) project. However the To-Do-List is
generated without indicating which task belongs to which inserted project.

Is there a way to edit this report to show this? Task ID doesn't help either.

Thanks

Rach,
First of all, there is no need to post twice. All that does is
potentially waste our time.

All you need to do is to add the Project field to the Gantt Chart view
(assuming the Gantt Chart view table is the one selected for the report
- The Entry table is the default). Then when the "to do list" Report is
selected, the associated subproject will be shown.

John
Project MVP
 