dave
Hi,
I've got a project with a number of tasks that have dependencies.
I wanted to 're-arrange' the tasks so the Gantt looks a bit more clean and
tidy and hasn't got lines going all over the place.
I've looked at microsoft article that basically says "just drag & drop"
[http://office.microsoft.com/en-gb/assistance/HA012111441033.aspx]
However, when I do this SOME of my tasks change their dates !!!!
Why is this happening and how can I stop it ?
In my scenario Task 28 has a predecessor of Task 132, however after dragging
to be by task 132 it also 'inherits' a new predecessor [task 131] even though
this has nothing to do with it.
I've got a project with a number of tasks that have dependencies.
I wanted to 're-arrange' the tasks so the Gantt looks a bit more clean and
tidy and hasn't got lines going all over the place.
I've looked at microsoft article that basically says "just drag & drop"
[http://office.microsoft.com/en-gb/assistance/HA012111441033.aspx]
However, when I do this SOME of my tasks change their dates !!!!
Why is this happening and how can I stop it ?
In my scenario Task 28 has a predecessor of Task 132, however after dragging
to be by task 132 it also 'inherits' a new predecessor [task 131] even though
this has nothing to do with it.