T
Thomas
I have an MSP2000 schedule with many tasks, all for one resource, but
none are 100% of that resource.
The tasks are all meant to run concurrently with the use of the resource
from 5% to 49%.
Four questions.
1. The single most intensive task I like to set at 100% and somehow
inform MSP that it should supply as much of the leftover resource to
that task. Can I do that?
2. What I have done is to figure add the total resource use of the less
intensive tasks. That comes to 51%. So I allocated 49% to the most
intensive task, and that seemed to work, but strikes me as being
intensively manual.
3. I changed some of the details on the intensive task and upon leveling
there were some days when the resource was used only 75% total. I had
to remove and reassign the resource, at 49%, to the intensive task in
order for MSP to schedule the single resource at 100% on every working
day. Again, this strikes me as being intensively manual. Is there
another way?
4. Finally, if I left the intensive task as nominally requiring 100% is
there a way to inform MSP to allocate resource capacity left over, even
if not 100%, to that task? What it appears to be doing now is simply
delaying the start of the task until 100% of the resource is available,
scheduling days where the resource is used 40%.
Thanks.
Thomas
--
Three stages of truth for scientists:
(1) It's not true.
(2) If it is true, it's not very important.
(3) We knew it all along.
Leo Szilard, (1898-1964, Key figure in the Manhattan Project)
none are 100% of that resource.
The tasks are all meant to run concurrently with the use of the resource
from 5% to 49%.
Four questions.
1. The single most intensive task I like to set at 100% and somehow
inform MSP that it should supply as much of the leftover resource to
that task. Can I do that?
2. What I have done is to figure add the total resource use of the less
intensive tasks. That comes to 51%. So I allocated 49% to the most
intensive task, and that seemed to work, but strikes me as being
intensively manual.
3. I changed some of the details on the intensive task and upon leveling
there were some days when the resource was used only 75% total. I had
to remove and reassign the resource, at 49%, to the intensive task in
order for MSP to schedule the single resource at 100% on every working
day. Again, this strikes me as being intensively manual. Is there
another way?
4. Finally, if I left the intensive task as nominally requiring 100% is
there a way to inform MSP to allocate resource capacity left over, even
if not 100%, to that task? What it appears to be doing now is simply
delaying the start of the task until 100% of the resource is available,
scheduling days where the resource is used 40%.
Thanks.
Thomas
--
Three stages of truth for scientists:
(1) It's not true.
(2) If it is true, it's not very important.
(3) We knew it all along.
Leo Szilard, (1898-1964, Key figure in the Manhattan Project)