One task with two resources
Task = 8hrs
Resource 1 - 100%
Resource 2 - 50%
Resource usage view shows Resource 1 at 8hrs and Resource 2 at 0.8hrs.
This is happening on a number of the tasks when you view the Resource Usage
View. However, most of the tasks are showing the right hrs for the resources.