I'm given to assign a 20 day task to a resource at 75% (i.e. he'll spend 75%
of each week) on this task. That means, it'll take him more than 20 days to
complete the project.
How do I go about doing that in MS-Project?
1. Do I change the max units first in the resource sheet to the resource
name at 75%?
2. Or what steps do I need to do to ensure the resource is set to 75%
availability per day on this task.
Any help will be greatly appreciated. Thanks.