I'm new the forums, but it looks like a great place to get help.
Here's my question...
I have an MS Project Plan created with tasks, dependencies, and effort
(broken down by each project phase). I know which resources should be
assigned to each task. Seperately, I created a detailed Resource Plan with a
list of all resources, hours per resource, and which tasks they should be
involved with.
The project is complex, with approximately 15k workdays over 100 tasks, and
around 40-50 FTEs. What is the easiest way to load my MPP with resources,
while maintaining the right number of hours per resources per phase? Is
there any way to do this (add-in tool perhaps?) besides manually adding
resources to tasks, leveling, hoping the hours match what my Resource Plan
says, and then reallocating?
Thanks in advance for your help!!
Sanjay.
I'm new the forums, but it looks like a great place to get help.
Here's my question...
I have an MS Project Plan created with tasks, dependencies, and effort
(broken down by each project phase). I know which resources should be
assigned to each task. Seperately, I created a detailed Resource Plan with a
list of all resources, hours per resource, and which tasks they should be
involved with.
The project is complex, with approximately 15k workdays over 100 tasks, and
around 40-50 FTEs. What is the easiest way to load my MPP with resources,
while maintaining the right number of hours per resources per phase? Is
there any way to do this (add-in tool perhaps?) besides manually adding
resources to tasks, leveling, hoping the hours match what my Resource Plan
says, and then reallocating?
Thanks in advance for your help!!
Sanjay.