S
Steve Scott
If I have 11 testers who are only available in any given month for 15.4 days.
Do I simply just set the resource availabilitry as 1540% or must I also set
the working calendar in each month to total only 15.4 days? How do I do this
and take the 0.4 days into account?
Do I simply just set the resource availabilitry as 1540% or must I also set
the working calendar in each month to total only 15.4 days? How do I do this
and take the 0.4 days into account?