Resource Grouping

A

Amin V

I am a production planner for a manufacturing company. I want to assign
tasks to each group and let the group leader decide which particular part of
the task should be handled by which employee.
Is there a way to group the resouces together so I can assign the task to
the group and find out the group's availability?
thanks
 
R

Rod Gill

The only thing you can do is assign tasks to the resource managers and leave
them to re-assign. Set the Max Units for each resource to the total number
of tem members.
 