T
Trevor
Hello,
I'm back again with another question related to resource
allocation.
I have set up a master resource file that is separate from
my project files.
(1) I want to know if there is an easy way to replace a
resource for specific tasks per project file.
For example, I've got tasks that involve one - four
resources. One of my resources is going on vacation, I
want to replace them with another resource during that
period of time only. Otherwise, if I don't replace the
resource, when I resource level project appears to
continue the task when the resource returns (even if there
are more resources for the task).
(2) I have two resources working on a task. One is going
on vacation, the other should continue the task.
Everytime I resource level, MS Project splits the task
activity to continue only when 'both' resources are
available again, instead of allowing the one to continue
during that time.
(2b)How do I stop a shared resource from working on a task
on a specific date for a particular project and have that
info considered while resource leveling?
The task are usually set up as effort driven, fixed units.
I haven't seen how this is handled in the Project 2000
Bible.
I'm back again with another question related to resource
allocation.
I have set up a master resource file that is separate from
my project files.
(1) I want to know if there is an easy way to replace a
resource for specific tasks per project file.
For example, I've got tasks that involve one - four
resources. One of my resources is going on vacation, I
want to replace them with another resource during that
period of time only. Otherwise, if I don't replace the
resource, when I resource level project appears to
continue the task when the resource returns (even if there
are more resources for the task).
(2) I have two resources working on a task. One is going
on vacation, the other should continue the task.
Everytime I resource level, MS Project splits the task
activity to continue only when 'both' resources are
available again, instead of allowing the one to continue
during that time.
(2b)How do I stop a shared resource from working on a task
on a specific date for a particular project and have that
info considered while resource leveling?
The task are usually set up as effort driven, fixed units.
I haven't seen how this is handled in the Project 2000
Bible.