N
NewsGroup
There is an overallocation problem with my Resource Scheduling.
I had split my window into 2 with Resource Usage view at the top and the
Resource allocation view at the bottom.
While attempting to eliminate overallocation I found 2 ways.
One is just pushing the task in the lower pane.
The other is entering elapsed duration.
I dont know what elapsed duration mean?
Is there a differnece between pushing the Start date of the task and
entering elapsed duration?
If there is, what is the difference?
Meena
I had split my window into 2 with Resource Usage view at the top and the
Resource allocation view at the bottom.
While attempting to eliminate overallocation I found 2 ways.
One is just pushing the task in the lower pane.
The other is entering elapsed duration.
I dont know what elapsed duration mean?
Is there a differnece between pushing the Start date of the task and
entering elapsed duration?
If there is, what is the difference?
Meena