One wrinkle to consider about this. When you say you want your employees
to work a 6 hour project day, do you mean that they will be on the property
*and available to work on the project* 8 working hours per day but will only
be able to average 6 of the 8 on project-specific activities, or do you mean
that a designated, specific 6 hours per day, say 10am to 5pm, will be
available to the project with the other 2 exact hours, 8am to 10am, will
*always* be dedicated to non-project related activities? If it's the former
it's an 8 hour calendar with a maximum availability of 75% while the latter
is a 6 hour calendar with a maximum availability of 100%. The problem with
the second is that you would not ever be able to schedule a task to run
during the two hours you set aside - it would always be considered
non-working time. If you used my example times, work on any tasks could
ONLY take place between 10am and 5pm and it would be impossible to start a
task at 8am. My advice would be to go with the former or even better, not
even try to micromanage it in such detail. I have to wonder if it's really
necessary to account for every minute of the employee's day - isn't it
enough to say that Task X can start on Monday and end on Thursday - does it
really matter if that time period represents 32 man-hours of actual effect
solely focussed on task X to the exclusion of everything else versus 32
man-hours of which 8 are just understood to be undefined overhead hours such
as email, bathroom breaks, misc meetings, etc. Before opening up such a can
of worms and trying to structure their day in such detail, I suggest
thinking about what real improvements might actually to be gained by doing
so. Only you can answer that for your situation, of course, but 99% of the
time it doesn't seem worth it to me - just because we can be so detailed
doesn't mean we ought to be. Just a thought ....
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
RobinT said:
We are currently trying to implement Project 2007 Pro, Server and Web
Access
Enterprise wide. I am having difficulty understanding exactly how to use
the
calendars to set non-working time. We want the employees in our dept. to
have
6 hour project work days, not 8. This would not be enterprise wide, only
for
our area. Then we want a way to keep track of how that non-working time is
used. I think I need to use a calendar and a project but am not sure how
to
set duration, finish date, etc. I have looked for training and
unfortunately
there just isn't any for 2007 yet. Please help.