Separate columns for start times and dates?

R

RNW

I know I can go to Tools>Options>View to set a date format that shows time
as well as date. But is there any way to put the start and end times in a
column separately from the start and end dates? It would just be easier to
enter the information if they were in separate columns...

Thanks.
 
J

JulieS

Hi RNW,

You shouldn't be entering in Start dates and times into a Project file.
The start date and times should be calculated based upon the project
calendar, task duration, and dependency relationships (links), etc. You
may like to have a look at Mike Glen's series of articles on MS Project
at:
http://project.mvps.org/mike's_tutorials.htm

Article 1, 2, and 3 should get you started.

I hope this helps. Let us know how you get along.

Julie
 
J

Jan De Messemaeker

Hi,

I can think of a way to show date and time separately through VBA and maybe
even through a formula but to transfer such custom foelds into life data
such as constraint date would definitely, surely, require VBA programming.
HTH
 