Set start date in hours instead of a date

G

George

I want to set a start date for several activities starting 150 hours after
the beginning of the project. Does someone knows how to do this without
calculating how many days would this take, just by giving the input of 150
hrs?
Thanks!
 
J

John

George said:
I want to set a start date for several activities starting 150 hours after
the beginning of the project. Does someone knows how to do this without
calculating how many days would this take, just by giving the input of 150
hrs?
Thanks!

George,
Sure, just enter the following as a predecessor to each of those tasks
(assuming task ID 1 starts on the Project Start Date).
1SS+150h.

Note that you only have to enter it for one task and then use "fill
down" for the other tasks.

Hope this helps.
John
Project MVP
 